Under Construction

  • Updated on 9/18/18

    The project consists of various drainage improvements associated with street drainage and neighborhood concerns regarding drainage. The following locations are included in the project:
    Alarcon Alley #1 between Aubrey St. south to Lereaux St. – Project is to address drainage and sediment concerns associated with the alley.                                            Robinson Drive Storm Drain off Hill Crest Lane. A new storm drain will be installed to convey drainage into the Robinson Drive storm drain system. The alleys in the area will be paved with the project.
    915 Country Club Drive – Re-design the driveway (which has been elevated over the years with pavement overlays) and drainage along the side of the road.
    Divinity Circle – Remove and repave the cul-de-sac. The road is failing and drainage is currently ponding in the road during storm events.
    1816 Boardwalk Avenue – reinstall scupper drain to low point of the road. Currently, the scupper drain is not in the low point of the road and drainage jumps the curbing causing erosion damage near a culvert the City maintains.
    5587 Goldenrod Way – Repair erosion hazard and re-install an outlet structure that has been undermined.
    Samaritan Way between Lakeview Road and Magnolia Lane -Grated drains are failing along the side of the road and the road in the area is deteriorating. The project will reinstall new catch basins and remove poor pavement sections before repaving the road.
    Thumb Butte Road between 1803 and 1717 – Add curbing along the south side of the road, to prevent drainage from flooding adjoining property.

  • Updated on 9/18/18

    Pavement rehabilitation work along Willow Creek Road and Gail Gardner Way is scheduled to commence the week of September 10.  Improvements include the removal and replacement of existing asphalt pavement along Gail Gardner Way, from Iron Springs Road to Willow Creek Road, and along Willow Creek Road, from Mitchell Road to the intersection of Green Lane and Pulliam Drive.  Additional work includes replacing handicap ramps, sidewalks, and curb and gutter as needed.

    Once complete, these improvements will extend pavement life and improve the driving surface for motorists well into the future.  The project is scheduled for completion in fall 2018.

  • Updated on 9/18/18

    The Granite Creek Dam Outlet Rehabilitation Project generally consists of the replacement of the inoperable 36″ large diameter valve that controls discharges for Watson Lake, and the sealing and abandonment of the inoperable 48″ large diameter valve, both at Granite Creek Dam constructed in 1919. The proposed 36″ replacement valve is to include a 12″ bypass. The project will provide for operation of the valves from the dam crest via flexible operators. The project also includes the replacement of existing upstream trash racks and installation of new slide gates.

     

  • Updated on 9/18/18

    The project will remove two aged lift stations (1958) from the collection system by extending approximately 1,500 LF of new 8-inch gravity sewer mains to serve the City parcels located on Mingus, Douglas and Delano Avenues. The existing force mains will be drained and plugged, and the existing wet wells, pumps, and electrical equipment will be removed as part of the project.

    The project was identified by the Wastewater Model as a project that will increase operational efficiency of the wastewater collection system. At the completion of this project, the wastewater operations group will have two less lift stations to operate and maintain.

     

  • Updated on 9/18/18

    The Robinson Drive Improvements Project generally consists of the reconstruction of Robinson Drive from Gurley Street to the County boundary south of Newport Drive, including water, sewer, and drainage improvements.

     

  • Updated on 9/18/18

    Undersized water mains in the Dexter Neighborhood are being abandoned in the alleys and new water mains are being installed in the streets. Water services for each parcel are being rerouted from the alley to the street and then tied back into the private water service lines. The streets involved in this construction will be resurfaced.

    The area involved with this construction project include: Bird Street North of Hillside, Ruth Street North of Hillside Drive, Dameron Drive from Hillside Drive to Comfort Avenue, Comfort Avenue from Dameron Drive to Campbell Street, Campbell Street from Whipple Street to Hillside Drive, Campbell Street from Comfort Avenue to Sonora Drive, and Sonora Drive from Campbell Street to the end of road.

     

  • Updated on 9/18/18

    • This project will replace two existing booster pump stations at the corner of Heather Heights and State Route 69. The pump stations being replaced feed the water service areas known as Zone 56 (SR 69 corridor/Prescott Canyon Estates) and Zone 76 (Prescott Resort).  Replacement of the pump stations will address deficiencies as identified by the City’s 2013 water model.  The upgraded pump stations will provide required pressures, residential/commercial fire flows to the two zones, and will enhance water movement to the other surrounding water system zones..

 

 

CONTACT

  • City Construction Projects
  • Tim Sherwood
  • Construction Services Administrator
  • Public Works Building

    433 N Virginia St

  • 928-777-1130

NEWS

Celebration in honor Ernest A. Love and all WW I Veterans October 4

Posted on September 21, 2018

The City of Prescott, American Legion Post 6, and the Prescott Chamber of Commerce are hosting a celebration of the life and sacrifice of Ernest A. Love, and all veterans, with a reception on Thursday, October 4, 2018 at 5:30… Read more »

View the Latest