Projects in Design

When a project has been approved in the budget by the City Council, it moves from the Capital Improvement Plan (CIP) list into the active Design phase.  The Design phase is an exploratory process where City staff identifies key elements of the project, researches information needed to implement the project, hires and Engineering firm to lead the design team and solicits public input.

The design of a project is a very important first step to identify construction elements to promote the timely delivery of the project with as little impact to neighboring properties as possible.

A Project Manager (PM) is assigned to each project on the CIP list.  The PM is the point of contact for the public and is responsible for guiding the engineering firm through the design process until a complete set of plans are approved by the City.

As the plans are developed, they go through phases of completion.  These phases are known as:

  • 15% plans (conceptual)
  • 30% plans (preliminary design)
  •  60% plans (design development)
  • 90% plans (pre-final design)
  • 100% plans (completed final design)

Public input on the design of a project is typically done around the 30%-60% plan phases.  A community open house meeting may be held by the City and design engineer to explain the project, answer questions and get input from the public.  By this time, enough information is known about the project to answer questions and have a good understanding of the needs of the project.

When the design of the project is complete, it will move on to the construction phase.  View projects in the “Construction” phase.

Resources

Maricopa Association of Governments (MAG) Standards and Details

A complete list of projects currently in design, is listed below:

  • Updated on 9/18/18

    The project will replace approximately 15,600 Lineal Feet (LF) of 24-inch to 48-inch gravity sewer trunk and branch mains near the Airport in the north Prescott area. The project will begin at the Airport Water Reclamation Facility and will run southerly to the Northern edge of the Granite Dells. Results of the Sewer Model Report and Centralization Analysis, determined that the existing Airport Trunk Main needs to be upsized for current flow demands and for the centralized build out scenario. This project is the 5th of 10 projects that will complete centralization of the Wastewater Treatment process. Centralization, when completed will combine all wastewater treatment processes at the Airport Water Reclamation Facility and decommission the Sundog Wastewater Treatment Plant.

     

  • Updated on 9/18/18

    This project is to design and drill a new production/recovery well based on the City’s Well Development Plan. The well site is anticipated to be located near the APS Solar Power Station located on City Parcel #103-01-023. The City intends to employ a Design/Build project delivery process, the primary objective is to bring the best available construction experience and expertise together to meet the project demands.

  • Updated on 9/18/18

    The project previously known as the Carleton Street/Alarcon Street Improvements Project has undergone an internal analysis to reconfigure the project to address the most immediate needs for pavement and utility improvements on Carleton Street and S. Cortez Street to deliver the greatest benefit to the community within a reasonable budget and time frame.  The project still consists of drainage, utility, and pavement improvements on Carleton Street from the entrance to Mile High Middle School to Cortez Street.  The project now includes utility and pavement improvements on S. Cortez Street from Carleton Street to Goodwin Street.

     

  • Updated on 9/18/18

    This project will design and construct new water main infrastructure to replace the undersized and aged water mains located in the Mile High area. This area is located in the Mile High Park Addition which includes Mile High Drive, Rose Garden Cove, Keen Street and Paar Drive. Approximately 2,790 LF of various size water mains will be replaced in this location.

     

  • Updated on 9/18/18

    The project is located along Karen Drive, Terrace Drive, Juniper Drive and Old Senator Highway. Approximately 5,000 LF of under size water mains will be replaced in this area.

  • Updated on 9/21/18

    The Goodwin Street Improvements Project generally consists of constructing roadway, drainage, streetscaping and pedestrian access improvements along Goodwin Street from Summit Street east to Marina Street, and along Summit between Goodwin and Hill Streets. Improvements will also include water, sewer and the addition of storm drains are also included.

     

  • Updated on 9/18/18

    The bridge on Overland Trail crossing Government Canyon is in substandard condition and requires replacement. Through an Intergovernmental Agreement the Arizona Department of Transportation is funding the majority of the bridge replacement and administering the design work and future construction.

  • Updated on 9/21/18

    This project is an in-house design.  Utility locating will take place this month with 30% plans expected by early October.  Construction should begin in early 2019.

  • Updated on 9/18/18

    The Hope Street Improvements Project generally consists of constructing roadway, drainage improvements and water main replacement on Hope Street from White Spar Road to Warne Street. Additional improvements include replacing the water main on Warne Street to loop into Hope Street.

     

  • Updated on 9/18/18

    The Penn Avenue/Eastwood Drive Improvements Project generally consists of constructing roadway improvements on Penn Avenue from Gurley Street to Carleton Street; Eastwood Drive from Carleton Street to Nevada Drive; Nevada Drive up to Devereaux Drive; and all cul-de-sacs west of Eastwood. The project will include pavement reconstruction, water and sewer system upgrades, a new storm drain system in Eastwood Drive, Acker Park Trailhead improvements, a regional storm detention system, and improved open space access.

     

  • Updated on 9/18/18

    The S. Washington Avenue/Goodwin Street Improvements generally consists of constructing roadway and pedestrian access improvements along E. Goodwin Street from S. Mt. Vernon Avenue to Penn Avenue, and along S. Washington Avenue from Gurley Street to the southerly termination of S. Washington Avenue. The project will include new curb and sidewalk installations as well as water, sewer and drainage will be upraded.

     

     

  • Updated on 9/21/18

    The Summit Avenue/McCormick/Beach Street Improvements Project generally consists of reconstructing the severely deteriorated concrete roadway with new asphalt pavement. The project will change Beach Street to a one way street from McCormick west towards Summit. New water and sewer upgrades are also included. The project will also include new storm drain improvements. Curb, sidewalk, and landscape improvements will be included as needed.

     

  • Updated on 9/18/18

    The project generally consists of replacing the aged and undersized water main and reconstructing the severely deteriorated pavement on Sundog Ranch Road from Prescott Lakes Parkway to the Yavapai Tribe boundary near Yavpe Connector.

    Due to budgetary constraints, the project will be designed and constructed in two phases, the first phase being the water main replacement.

     

  • Updated on 9/18/18

    The project is to direct additional sewer flows from the Sundog Wastewater Treatment Plant to the Airport Water Reclamation Facility. The project includes the construction of a new force main from a proposed lift station at the Veteran’s Administration Hospital Grounds north along Highway 89 to the northeast corner of Highway 89 and Prescott Lakes Parkway. The new force main will tie into the Sundog Trunk Main Phase A, which will be completed prior to beginning this project.

  • Updated on 9/18/18

    The Phase C Trunk Main will replace aging, undersized and failing clay and PVC pipe. The sewer main replacement project will reduce sanitary sewer overflows, reduce operations and maintenance costs, remove portions of the sewer system outside of the floodplain, and will complete the overall Sundog Trunk Main Project towards Centralization. The project is anticipated to replace approximately 12,000 lineal feet of 12-inch through 30-inch diameter gravity sewer main at the following locations.

    1. From the intersection of Miller Valley Road and Brannen Avenue, southward on Miller Valley Road, along Miller Creek to a point just east of Miller Creek low water crossing on Lincoln Avenue.

    2. Starting at the eastern end of Sonora Drive, along the edge of Granite Creek under the La Guardia Bridge (Montezuma Street), through Granite Creek Park, across 6th Street and down Henry Street, parallel to E-Z Street, within the Yavapai Prescott Indian Tribe land (YPIT) and then through Veterans Administration (VA) land generally following the old Peavine railroad alignment to a connection designed in the Phase B Project at the southeastern edge of the VA solar Field.

    3. Branch connections to connect sewer mains that currently outfall into the existing sewer trunk main.

    The project will also include approximately 1,600 linear feet of 12-inch water main replacement at the following locations:

    The intersection of Miller Valley Road and Lincoln Avenue up to a point 80 feet north of the Miller Creek low water crossing on Lincoln Avenue.

  • Updated on 9/18/18

    The City of Prescott Transfer Station was built in 1991 when the Sundog Landfill was approaching capacity. The facility is intended to serve the solid waste disposal and transfer needs of Prescott and the surrounding unincorporated areas of Yavapai County. The Transfer Station was built to accommodate 250 tons of residential and commercial solid waste per day, and is currently processing approximately 200 tons per day.

    The Transfer Station Pavement Improvements Project generally consists of reconstructing the aged and deteriorating asphalt pavement at the Transfer Station with new, structurally stronger subgrade and base materials and fiber reinforced asphalt concrete pavement to effectively extend the functional life of paved surfaces at the Transfer Station.

  • Updated on 9/18/18

    The Washington Avenue/Churchill Street Reconstruction Project generally consists of constructing roadway improvements on N. Washington Avenue from Churchill Street to Sheldon Street, and on Churchill Street from N. Washington Avenue to Arizona Avenue.

     

  • Updated on 9/18/18

    This project will consist of design and replacement of the City of Prescott water booster facility (buildings, boosters, electrical, controls) located in the Town of Chino Valley. The new intermediate pump station, tanks and pipeline will reduce pipeline pressure and provide additional tank storage closer to Prescott. It is anticipated that there will be approximately 8-10MG of storage at the facility. The project will coordinate with upgrades to the Chino Valley pumping facility to adjust for lower operating pressures at the Chino Valley Facility.

  • Updated on 9/18/18

    The flood study has been awarded to JE Fuller Hydrology and Geomorphology, Inc.  The study is to re-evaluate the Willow Lake Tributary floodplain upstream of North Ridge Drive (approximately 3,000 feet), to update topographic discrepancies between the original study topography in 2008 and the updated 2016 topography.  The City is anticipating removing several residential structures from the floodplain at the completion of the study.  The flood study is anticipated to be completed and submitted to FEMA to review this winter.

     

  • Updated on 9/21/18

    This project will consist of relocating the existing Zone 7 pump station that feeds pressure zones east of Prescott Lakes Parkway, eastward to the new 1.5 MG water storage tank for pressure Zone 56, and relocated and upgraded to meet existing and future domestic and fire flow demands for this area. This project would include installation of new pumps, associated controls and appurtenances, and an above-ground building enclosure. This project would be constructed concurrent with the installation of the new Zone 56 1.5 MG tank and piping.

     

  • Updated on 9/18/18

    This project will include replacement of the existing Zone 16 Tank inside the Hidden Valley Ranch subdivision with a new 250,000 gallon tank, including tank access road improvements, upsizing of the water main in Haisley Road from Senator Highway to Valley Ranch Circle, increasing the capacity of the Virginia Pump Station, and upsizing of the water main from the termination of South Virginia Street to the Prescott Community Church property. The project will provide improved water delivery and increased fire protection to the area. Haisley Road between Senator Highway and Valley Ranch Circle will also be reconstructed concurrently with the water line improvements.

  • Updated on 9/21/18

    The Zone 24 & Zone 27 Water Main Piping Replacement Project will consist of various water distribution main improvements within water system Pressure Zone 24 and Zone 27 in the western part of Prescott. The project will include the installation of a new 12-inch water main from the Thumb Butte Drive and Sherwood Road intersection to the new Zone 27 Reservoir on Skyline Drive, and a new 12-inch water main from the Zone 24 Reservoir at Lookout Lane to the new Zone 27 Reservoir.

  • Updated on 9/18/18

    The project generally consists of replacing two existing 200,000 gallon water storage tanks with a single 1.5 million gallon water storage tank. The project includes replacing the existing Mingus Pump Station to meet demands and upsize the pipeline between the pump station and the new tank.

     

     

  • Updated on 9/21/18

    The Zone 56 Tank and Piping Project generally consists of constructing a new partially buried 1.5 million gallon pre-stressed concrete tank to be located north of Highway 69 west of York Motors. This tank will replace the existing 100,000 gallon welded steel tank located in Prescott Canyon Estates. An additional project element will include removing and replacing approximately 4,300 lineal feet of existing 8-inch CIP water line with a new 16-inch DIP water line.

     

CONTACT

  • City Construction Projects
  • Tim Sherwood
  • Construction Services Administrator
  • Public Works Building

    433 N Virginia St

  • 928-777-1130

FAQ

  • Project Managers contact information can be found by clicking on the + sign next to the project name on the list, then clicking on “Contact Information”.

  • Public meetings and information on projects can be found by clicking on the + sign next to the project name on the list, then clicking on “Public Meeting Notices” or by contacting the Project Manager at 928-777-1130.

NEWS

Celebration in honor Ernest A. Love and all WW I Veterans October 4

Posted on September 21, 2018

The City of Prescott, American Legion Post 6, and the Prescott Chamber of Commerce are hosting a celebration of the life and sacrifice of Ernest A. Love, and all veterans, with a reception on Thursday, October 4, 2018 at 5:30… Read more »

View the Latest