Under Construction

  • Updated on 5/21/21

    This project will include pavement preservation and surface remediation of approximately ten (10) lane miles of roadways, specifically Williamson Valley Road and Iron Springs Road. The project will remove the existing AR-ACFC surface treatment and replace with a chip seal and PMM application.  The AR-ACFC course has worn to the point where it needs to be removed and replaced.

  • Updated on 5/3/21

    The project generally consists of pulverizing and blending in place the existing asphalt pavement surface, base preparation of recycled base material and placement of new asphalt concrete at various locations throughout the City. The work also includes pavement repairs, the adjustment of utility covers to finish grade and the restoration of disturbed traffic striping. Please see the attached update for locations.

  • Updated on 5/3/21

    The project generally consists of milling existing asphalt pavement, performing base preparation and placing new asphalt pavement on various roadways at various locations throughout the City. The work also includes unsuitable subgrade repairs on an as needed basis, the adjustment of utility covers to finish grade and the restoration of disturbed traffic striping, curb, gutter and handicap ramp replacements. Please see the attached update for locations.

  • Updated on 9/2/21

    The project generally consists of pulverizing and blending in place the existing asphalt pavement surface, base preparation of recycled base material, and placement of new asphalt concrete atop. The roadways included in the project are: Prescott Heights Drive, Campbell Avenue, Flora Street and Black Drive. The work includes pavement repairs, the adjustment of utility covers to finish grade, some minor drainage repairs and the restoration of disturbed traffic striping.

  • Updated on 9/2/21

    The project generally consists of milling existing asphalt pavement, performing base preparation, and placing new asphalt pavement. The work includes repair on unsuitable subgrade on an as needed basis, the adjustment of utility covers to finish grade, and the restoration of disturbed traffic striping. The project may also include curb and gutter replacements as necessary. The first phase of the project will be constructed in the early Fall of 2021 and will include Wilkinson Drive from the Prescott Regional Airport, south to the new Corsair Drive roundabout intersection.

  • Updated on 9/2/21

    Prior to planned Yavapai County Storm Drain Improvements along Yampa Drive within the Ho Kay Gan Subdivision, the City of Prescott will be relocating and realigning existing water mains along Yampa Drive from Kiva Circle to Natani Circle to prevent conflicts with the new drainage infrastructure.

  • Updated on 9/2/21

    The project consists of the installation of approximately 6,200 lineal feet of new 24-inch ductile iron water main across vacant land to the new Intermediate Pump Station (IPS) Site currently under design. This is the second phase of off-site water main installation to the new IPS Site. The project also includes construction of a new access road to the IPS facility.

  • Updated on 9/2/21

    The project generally consists of removing four decommissioned drying beds composed mostly of reinforced concrete at the City’s Sundog Wastewater Collection Facility.  Also included is removal of some minor plumbing connections, crushing of the existing concrete, and using that concrete and other fill material to place fill in the general removal area to create a proposed building pad for future use by the Public Works Streets Division for snow removal equipment.

  • Updated on 9/2/21

    The Sunrise Boulevard Improvement Project involves reconstructing the pavement section of Sunrise Boulevard, between Sharp Shooter Way and Cactus Place. The project will also include replacement of curb and gutter as needed, and various drainage infrastructure.

  • Updated on 9/2/21

    The City of Prescott Water Production Facility, located in the Town of Chino Valley, is the City’s primary source for water production. This project will replace the existing water booster facility in Chino Valley and will build the new intermediate pump station and tanks located near the Prescott Airport. This project will create a reduction in transmission pipeline pressure, improve production redundancy and provide additional storage capacity closer to Prescott.

    City of Prescott Water Production Facility (Chino Valley):

    The existing booster station is located in the Town of Chino Valley at the City of Prescott’s Water Production Facility, 251 N. State Route 89 (APN 306-23-077C). This project will consist of design and replacement of the City of Prescott water booster facility (buildings, boosters, electrical, controls). The facilities were originally built in the 1940’s and updates have been made to the facilities throughout the years to keep pace with the growing demand.  The current facility is undersized to meet future demands and the existing equipment has reached the end of its service life.  The facility replacement will ensure safe and reliable water supply to the City of Prescott service area. It is anticipated that the new booster station facility will have a firm pumping capacity of 14.0 MGD. By completing this project, the City will be able to provide additional reliability through higher efficiency and modernized equipment (buildings, electrical components, piping).

    Intermediate Pump Station Facility:

    The new intermediate pump station site is anticipated to be located about 1 mile north of Pioneer Parkway and 1 mile west of Willow Creek Road on currently undeveloped land; the site will be accessed from the east from Willow Creek Road. This project will provide the infrastructure to supply required redundancy to the existing water delivery system. This increases the overall reliability of the City’s water supply system by allowing the airport production wells to support the entire water system. Additionally, growth in north Prescott requires that a second pump station be constructed at the Intermediate Pump Station Facility that serves the surrounding pressure zone, Zone 110. The storage capacity required to meet fire demand and development growth needs have been determined by the City’s water model. The anticipated storage required for the intermediate pump station facility is 10 MG with the ability to expand to 15 MG. The intermediate pump station and the Zone 110 pump stations are anticipated to have a pumping capacity of 17.5 MGD and 8.4 MGD, respectively. Both pump station capacities will be evaluated further and confirmed during design.

     

  • Updated on 9/2/21

    The Willow Creek Road Curve Realignment Project will consist of widening Willow Creek Road through the existing curve from the Deep Well Ranch roundabout south westward to Lone Elk Trail in the Saddlewood Development. The project will be done in conjunction with the widening of Willow Creek Road from the future intersection at Warrior Way to Lone Elk Trail. The work will include widening the road to four lanes with a raised center median, and includes new traffic signals at Lone Elk Way and Warrior Way. The City is also working with APS to relocate the existing 69Kv power poles.

  • Updated on 9/2/21

    The Zone 56 Tank and Piping Project generally consists of constructing a new partially buried 1.5 million gallon pre-stressed concrete tank to be located north of Highway 69, and west of York Motors. The tank will replace the existing 100,000 gallon welded steel tank located in Prescott Canyon Estates. An additional project element will include removing and replacing approximately 4,300 lineal feet of existing 8-inch CIP water line with a new 16-inch DIP water line. A portion of the new 16-inch main will be installed adjacent to SR 69 from Holiday Drive to the U-Haul entrance along the north side of the highway.

     

 

 

CONTACT

  • City Construction Projects
  • Tim Sherwood
  • Construction Services Manager
  • Public Works Building

    433 N Virginia St

  • 928-777-1130

NEWS

Jon Brambila Named Prescott Deputy Police Chief

Posted on September 10, 2021

Prescott Police Chief Amy Bonney has named Lt. Jon Brambila to the position of Deputy Chief, effective September 19, 2021.  Brambila was selected out of a competitive internal process.  “Lt. Brambila is a proven law enforcement professional who knows our… Read more »

View the Latest