Under Construction

  • Updated on 3/2/21

    This project is to design and drill a new production/recovery well based on the City’s Well Development Plan. The well site is anticipated to be located near the APS Solar Power Station located on City Parcel #103-01-023. The City intends to employ a Design/Build project delivery process, the primary objective being to bring the best available construction experience and expertise together to meet the project demands.

  • Updated on 3/2/21

    The project consists of removing and replacing the existing asphalt pavement along select streets within the Cliff Rose Subdivision. Pavement replacement will take place along Boardwalk Avenue, Marvin Gardens Lane, Oriental Avenue, Mediterranean Court, and Rycosa Lane. Additional work includes the restoration of disturbed traffic striping, adjustment of utility covers to finished road grade, and replacement of handicap ramps and curb and gutter in select areas throughout the project.

  • Updated on 3/2/21

    The City will be replacing an existing PVC water main on Equestrian Way in The Ranch subdivision due to a significant water main break that occurred in July 2020. The asphalt was also damaged to the extent that the street will be re-paved once the water main construction is complete. The project will include installation of new Ductile Iron water main on Equestrian Way and Equestrian Circle. This project is fast tracked and construction is expected to begin in the fall of 2020.

  • Updated on 3/2/21

    This project will design and construct new water main infrastructure to replace the undersized and aged water mains located in the Mile High area. This area is located in the Mile High Park Addition which includes Mile High Drive, Rose Garden Cove, Keen Street and Paar Drive. Approximately 2,790 LF of various sized water mains will be replaced in this location.

     

  • Updated on 3/2/21

    The project generally consists of removal and replacement of concrete sidewalk, curb and gutter, striping, scuppers and storm drain improvements at various locations within the City. The work also includes curb ramp installations, brush removal and general installation of landscape material.

  • Updated on 11/3/20

    The City’s Pavement Maintenance Program includes projects to Preserve, Rehabilitate and Reconstruct sections of roadways, as needed.

    Preservation projects include the application of pavement rejuvenators, fog seals, slurry seals, micro seals, crack sealing, chip seal and other surface applications to help extend pavement life. Roads that receive these treatments are in generally good condition, and not in need of a rehabilitation project.

    Rehabilitation projects will typically include mill and overlay projects. The roads that require these treatments are typically in poorer condition, but the underlying base section of the road is still in good condition and will allow for the installation of new surface course asphalt.

    Reconstruction projects include the full reconstruction of a roadway, up to and including the installation of new utilities. These roads have asphalt or concrete road surfaces that are typically at the end of their useful service life and may have utilities within the road section that are also in need of replacement.

  • Updated on 3/1/21

    The City’s Pavement Maintenance Program includes projects to Preserve, Rehabilitate and Reconstruct sections of roadways, as needed.

    Crack sealing will be performed on various streets throughout the City beginning in December 2020 and continuing through June 2021.

  • Updated on 3/2/21

    The City’s water operations have identified several locations to replace old and undersized water mains in the Wildwood Drive, Deerfield Road and Cliff Rose subdivision areas. The work will be separated into two projects. This project location will be in the Wildwood Drive and Deerfield Road (Hailsley Homestead) area, and will consist of replacing old undersized galvanized water mains.

  • Updated on 11/3/20

    This project generally consists of milling 4″ of the existing asphalt and replacing with new asphalt on Smoke Tree Lane. The work will include additional pavement repairs, the adjustment of utility covers to finish grade and the restoration of disturbed traffic striping. The project also includes curb, gutter and handicap ramp replacements as necessary.

  • Updated on 3/2/21

    The Willow Creek Road Curve Realignment Project will consist of widening Willow Creek Road through the existing curve from the Deep Well Ranch roundabout south westward to Lone Elk Trail in the Saddlewood Development. The project will be done in conjunction with the widening of Willow Creek Road from the future intersection at Warrior Way to Lone Elk Trail. The work will include widening the road to four lanes with a raised center median, and includes new traffic signals at Lone Elk Way and Warrior Way. The City is also working with APS to relocate the existing 69Kv power poles.

  • Updated on 3/2/21

    This project will include replacement of the existing Zone 16 Tank inside the Hidden Valley Ranch subdivision with a new 250,000 gallon tank. The project will also include tank access road improvements, upsizing of the water main in Haisley Road from Senator Highway to Valley Ranch Circle, increasing the capacity of the Virginia Pump Station, and upsizing of the water main from the termination of South Virginia Street to the Prescott Community Church property. The project will provide improved water delivery and increased fire protection to the area. Haisley Road between Senator Highway and Valley Ranch Circle will also be reconstructed concurrently with the water line improvements.

 

 

CONTACT

  • City Construction Projects
  • Tim Sherwood
  • Construction Services Manager
  • Public Works Building

    433 N Virginia St

  • 928-777-1130

NEWS

Update from the Mayor on Negotiations between AED and the City of Prescott

Posted on February 26, 2021

City expects at least two study sessions and public hearing Prescott Mayor Greg Mengarelli reports that negotiations between the City of Prescott and Arizona Eco Development (AED) are progressing in a very positive manner, and that there is every reason… Read more »

View the Latest