Skip to Content or Accessibility Information

City Construction Projects

Are you curious about what construction projects are taking place throughout Prescott? Well, you've come to the right place! Below you will find a list of construction projects that are currently underway as well as those projects that are still pending.

For information on the status of construction projects please call the City of Prescott Public Works Department at 928-777-1130.

Completed Projects

During 2010, the City contracted with a professional engineering firm to complete the Sundog Wastewater Treatment Plant (WWTP) and Airport Water Reclamation Facility (WRF) Capacity and Technology Master Plans. The study revealed that wastewater BOD and TSS strength at both treatment plants have nearly tripled since the most recent upgrade (1998) lowering the treatment capacity for the Airport WRF to 1.2 MGD. Currently, average daily flows to the plant are 1.1 MGD; therefore plant expansion is necessary to handle committed capacities and projected growth in the area. The treatment capacity recommended for the next phase of the Airport WRF was established at 3.75 MGD. Three phases are recommended from the Master Plan with a total recommended build-out capacity of 9.6 or 15 MGD (dependant on the City's decision for one centralized treatment plant in the future).

The City has completed contracts with Water Works Engineers for the design of the expansion project and PCL/Fann Environmental Joint Venture as the Construction Manager at Risk (CMAR). The final design plans were completed in early Fall of 2012. The CMAR contract for construction was awarded by City Council on October 23, 2012 and the notice to proceed for construction was given on November 12, 2012.

During the weeks of November 26th through December 14th, the subcontractor Fann Contracting be graded the site. Truck traffic will be minimal with equipment deliveries to the project.

The construction phase of the project will last approximately 2 year.

PDF APWA Project of the Year Submittal

PDF Airport WRF Council Presentation 10-23-12

PDF AWRF Capacity and Technology Master Plan (large file, please be patient)

Last updated: Tuesday, March 3, 2015 at 4:47 PM

The project generally consists of rubberized chip seal on various City streets, conventional asphalt chip seal on previously unpaved City streets and alleys, the adjustment of utility frames and covers to finish grade, various pavement repairs, and the restoration of disturbed traffic striping.

Bid advertising occurred in May, 2013. Construction began in July, 2013.

Last updated: Thursday, February 6, 2014 at 9:09 AM

In March, 2013, the City Council approved code changes that give the City discretion to replace or rebuild sidewalks subject to availability of funds in any given year. The Council has since then approved an annual budget for sidewalk repairs.

City staff has conducted a sidewalks condition assessment in the downtown area of the city and is in the process of developing engineered plans for repairs and replacement of dilapidated sidewalks.

Last updated: Friday, August 15, 2014 at 2:15 PM

The FY 13/14 Pavement Rehabilitation Project generally consists of milling existing asphalt pavement and replacing with new asphalt pavement on selected streets, and the construction of an AR-ACFC pavement overlay on arterial streets. The work includes crack sealing on an as needed basis, pavement repairs where needed, the installation of crack reducing pavement fabric, the adjustment of utility covers to finish grade, and the restoration of disturbed traffic striping. The selected streets are:

Sheldon Street from Montezuma Street to Aven Drive, Marina Street from Sheldon Street to Gurley Street, Whipple Street from Miller Valley Road to Montezuma Street, Pleasant Street from Gurley Street to Goodwin Street, Iron Springs Road at Meadowridge Drive, and Ruth Street along the Prescott High School frontage.

The plans and specifications are complete. Bid advertising was done on March 10, 2013.

Last updated: Tuesday, March 3, 2015 at 4:49 PM

This project consists of construction of new water main improvements and service lines in Miller Valley Road, Walnut Street, Division Street, Osburn Street, Madison Avenue east of Miller Valley Road, and the alley west of 1st Street. The existing water mains in the alleys east and west of Walnut Street will be abandoned. All work done in Miller Valley Road will be performed at night starting on May 5th.

Capital Improvements LLC was the low bidder on this project. They will begin installing new water service lines in Miller Valley Road which will be done at night between 6:00 P.M. to 5:00 A.M. This portion of construction will take approximately two weeks. Construction of a new 6-inch Water Main will also commence on Walnut Street.

Last updated: Tuesday, March 3, 2015 at 4:49 PM

The FY 2014 Pavement Preservation Project generally consists of the construction of approximately 150,000 square yards of Type III Microsurfacing on State Route 89, Ruth Street, Iron Springs Road, and Williamson Valley Road, and the construction of approximately 62,200 square yards of Type II Slurry Seal Coat on residential streets in the Pinon Oaks (North) Subdivision. The project includes the restoration of disturbed traffic striping. The project includes pavement preservation work at the Prescott Municipal Airport Administration Parking Lot and the Prescott Municipal Airport Bottleneck Ramp.

The plans and specifications have been completed by City staff and bid advertising was held on March 2, 2014.

Last updated: Tuesday, February 3, 2015 at 2:56 PM

Rosser Street Reconstruction, Phase II: The purpose of the project is to reconstruct Rosser Street from South Blooming Hills Drive to SR 89. The project includes replacement of the aged and deteriorated asphalt pavement, upgrade of the old water system, extension of the existing sewer main, and drainage improvements. The contract for the project has been awarded to CLM Earthmovers, LLC.

Questions regarding the project should be directed to the City Project Manager, George Henderson at (928) 777-1130.

PDF

PDF

Last updated: Monday, July 7, 2014 at 11:31 AM

White Spar Road - The White Spar Waterline Relocation project, from Copper Basin Road to Apache Drive will include the installation of new 12-inch Ductile Iron Pipe waterline on SR89-White Spar Road from Copper Basin Road to Apache Drive in advance of the upcoming ADOT road improvement project.

Additional improvements will include installation of new water meters, fire hydrants, tie-ins to existing water mains and services, and removal of an existing 6-inch water main within the same corridor. The Watkins/Mendoza Companies has been awarded the construction contract. Construction began the week of August 12th, 2013 and is anticipated to be completed in November.

Questions regarding the project should be addressed to the City Project Manager, Tim Sherwood at (928) 777-1130 or email to tim.sherwood@prescott-az.gov

Last updated: Friday, February 21, 2014 at 3:53 PM

The Willow Creek Dam Repairs Project consists of the removal and replacement of damaged concrete surfaces on Willow Creek Dam. Project work includes saw cutting, hydro demolition concrete removal, repair and replacement of concrete surfaces with epoxy bonded concrete patches, new handrail with steps and walkway installation, and security fence installation.

Last updated: Tuesday, February 3, 2015 at 2:57 PM

The City will be performing maintenance work at the intersection of Willow Creek Road and Rosser Street from Monday, November 17 through Friday, November 21, 2014.

Rosser Street Closure:

Northbound and southbound vehicles turning eastbound onto Rosser Street at Willow Creek will be detoured to Flora Drive and Northside Drive.

Willow Creek Road Restrictions:

Traffic lanes will be restricted on Willow Creek Road at the Rosser Street intersection.

Detour routes will be clearly marked.

Motorists are advised to use alternate routes whenever possible.

Last updated: Tuesday, March 3, 2015 at 4:24 PM