Skip to Content or Accessibility Information

City Construction Projects

Are you curious about what construction projects are taking place throughout Prescott? Well, you've come to the right place! Below you will find a list of construction projects that are currently underway as well as those projects that are still pending.

For information on the status of construction projects please call the City of Prescott Public Works Department at 928-777-1130.

Projects Currently Under Construction

This project is for street, water quality and streetscape improvements on Alarcon Street from Sheldon Street to E. Gurley Street. Improvements to Alarcon Street include pavement replacement. This project will also include streetscape beautification, and drainage improvements on Alarcon Street. The pavement surface has deteriorated with age and full reconstruction is required.

Project plans are nearing 30% design and a public meeting for information and input is scheduled for March 23, 2016. Please see flyer for Public Meeting below.

PDFMarch 23, 2016 Public Meeting Flyer

Last updated: Wednesday, August 24, 2016 at 2:13 PM

project update not available      Traffic Update / Street Closure not available

The Autumn Breeze Street Improvement Project generally consists of constructing roadway, drainage and pedestrian access improvements along Autumn Breeze from Nathan Lane to Spring Trail.

The design of the project is at 100% and being prepared for construction. Meetings for the project have been held with individual residents immediately affected by the project.

City Contact Information Project Manager: Jeff Low 777-1643 Email: Jeff.Low@prescott-az.gov

Last updated: Wednesday, April 13, 2016 at 2:01 PM

PDF Project Update      Traffic Update / Street Closure not available

The project goal is to realign, redesign and construct Crystal Lane from Ruger Road intersection with Deep Well Ranch Road to Airport Entrance along Janine Drive. In addition to the roadway pavement improvements, water, sewer and drainage improvements will be constructed. A small parking area is being considered northerly of the realigned roadway to better serve airport tenants.

Project plans are nearing 90% design. Construction is tentatively scheduled for later this calendar year.

Last updated: Wednesday, August 24, 2016 at 2:13 PM

project update not available      Traffic Update / Street Closure not available

The FY 2016 Pavement Rehabilitation Project generally consists of milling and asphalt pavement overlay and pavement resurfacing. The resurfacing includes multi-layer and single layer coats of rubber chip seals, micro-surfacing, and slurry seal coats. The project includes the placement of a conventional asphalt chip seal coat on previously unpaved streets and alleys. The project includes the adjustment of utility covers to finish grade and the restoration of disturbed traffic striping.

Construction is nearly complete with a final portion of the mill paving to occur later this fiscal year.

City Contact Information Project Manager: Steve Guizzo 777-1130

Last updated: Monday, March 14, 2016 at 2:55 PM

Project Update      Traffic Update / Street Closure not available

FY17 Pavement Rehabilitation and Preservation Project

Last updated: Tuesday, August 30, 2016 at 8:20 AM

Project Update      Traffic Update / Street Closure not available

The first part of the project is to evaluate the overall drainage in the Alberson Wash to determine the repairs or replacement of the Hummingbird Way and other culverts along the Wash. The evaluation has been completed and found that the Hummingbird Way and Sunrise Way culverts are in need of replacement. The project is to design and construct necessary drainage improvements.

The project plans are at the 100% level and construction is tentatively scheduled for this fiscal year.

PDFHummingbird Way Vicinity Map

Last updated: Tuesday, June 14, 2016 at 4:49 PM

Project Update      Traffic Update / Street Closure not available

This will complete the third phase of utility improvements in the Campbell Street area south of Whipple Street and north of Madison Avenue and will replace existing deficient mains (age, condition, capacity) with new water mains.

Project plans are nearing 90% design and a public meeting for information and input will be scheduled in the near future.

Questions regarding the project should be directed to City Project Manager, Ben Burns at (928) 777-1130.

Last updated: Wednesday, August 24, 2016 at 2:14 PM

project update not available      Traffic Update / Street Closure not available

The Smoke Tree Lane Pavement and Utility Upgrade Project generally consists of repaving Smoke Tree Lane from Willow Creek Road to Tabosa Drive, reconstructing the pavement structure on Smoke Tree Lane from Tabosa Drive to Birchwood Cove, and construction of a new 18" water transmission main from Willow Creek Road to Birchwood Cove.

The project is currently out to bid for construction to begin in April/May 2016.

Questions regarding the project should be directed to City Project Manager, George Henderson at (928) 777-1130.

Last updated: Friday, June 3, 2016 at 2:34 PM

Project Update      Traffic Update / Street Closure not available

The Tank Maintenance Program generally consists of making repairs and maintenance to existing water storage tanks to stop leakage and prevent future leakage. The first water tank programmed for rehabilitation is the South Tank at the southerly terminus of S. Washington Avenue.

The project plans are at 100% design and will be under construction in Fall 2016.

City Contact Information Project Manager: George Henderson 777-1130

Last updated: Wednesday, August 24, 2016 at 2:20 PM

PDF Project Update      Traffic Update / Street Closure not available

The project consists of reconstruction of Walker Road with new asphalt concrete pavement and placement of curb and gutter, sidewalk, and drainage and water line improvements. The project limits are from the SR 69 intersection to the South City limits.

The project is currently out to bid with construction tentatively scheduled to begin in April/May 2016.

If you have questions, please contact Ben Mokhtari, Public Works Project Manager at (928) 777-1653.

Last updated: Tuesday, May 10, 2016 at 10:29 AM

Project Update      Traffic Update / Street Closure not available

The project consists of construction of a realigned Willow Creek Road (WCR) between Pioneer Parkway and Deep Well Ranch Road Roundabout, and approximately 7,500 feett of 12-inch diameter waterline from the intersection of Willow Creek Road / Pioneer Parkway to the existing main at the intersection of MacCurdy Drive / Club House Drive.

The project is currently under construction and is scheduled for completion by October 2016.

Last updated: Monday, March 14, 2016 at 2:59 PM

Project Update      Traffic Update / Street Closure not available